Contaminated Sites Regulation, B.C. Reg. 375/96
Section 7.1
Duty to provide director with summary of site condition
Cite as Contaminated Sites Regulation, B.C. Reg. 375/96, s. 7.1 · last amended July 1, 2026 · read from BC Laws on November 17, 2026
The text
(1) A person applying for, requesting or seeking approval, consideration, review or a determination of any of the following in relation to a site must provide a summary of site condition, together with a recommendation by an approved professional in respect of the matter, to the director:
(a) a determination under section 44 of the Act [determination of contaminated sites];
(b) a determination under section 50 of the Act [minor contributors];
(c) a voluntary remediation agreement under section 51 of the Act;
(d) an approval in principle under section 53 (1.1) of the Act;
(e) a certificate of compliance under section 53 (3) of the Act;
(f) Repealed. [B.C. Reg. 133/2022, App., s. 4.]
(g) if the site is one to which Part 5 of the Act applies, a transfer agreement referred to in section 67 (1) (a) [advanced exploration sites] or 68 (1) (a) [producing or past producing mine sites] of that Part;
(h) if the site is one to which Part 5 of the Act applies, indemnification for the site under the Financial Administration Act;
(i) a covenant to be registered under section 48 (1) of this regulation;
(j) a preliminary site investigation report;
(k) a human health risk assessment or environmental risk assessment report;
(l) a detailed site investigation report;
(m) a remediation plan;
(n) a confirmation of remediation report;
(o) a report respecting local background concentrations of substances.
(2) Repealed. [B.C. Reg. 179/2021, s. (c) (ii).]
Read the Contaminated Sites Regulation on BC Laws ↗
Made under Environmental Management Act, SBC 2003, c. 53.