(1) The records and plans required under the following provisions of this regulation are prescribed for the purposes of section 38 of the Act:
(a) Part 5 [Programs and Plans];
(b) section 33 [emergency response plan];
(c) section 38 [decommissioning and restoration plan];
(d) section 40 [suspensions].
(2) Subsection (1) does not apply in relation to a record required under section 18 [construction programs and plan] after the date that is 3 years after the permit holder gives a notice of operation start.
Read the Renewable Energy Projects Regulation on BC Laws ↗