The text

(1) A permit holder for a renewable energy project must decommission the facility if the permit holder (a) ceases operation of the facility, or (b) suspends operation of the facility for 24 months. (2) A renewable energy facility is decommissioned for the purposes of this section if the permit holder removes from the operating area of the permit all structures and equipment associated with the facility. (3) A permit holder for a renewable energy project must ensure that the decommissioning of the facility is carried out safely.
Read the Renewable Energy Projects Regulation on BC Laws ↗

Made under Energy Resource Activities Act, SBC 2008, c. 36.