Renewable Energy Projects Regulation, B.C. Reg. 28/2026
Section 39
Progressive restoration
Cite as Renewable Energy Projects Regulation, B.C. Reg. 28/2026, s. 39 · last amended September 14, 2026 · read from BC Laws on November 17, 2026
The text
(1) A permit holder for a renewable energy project must restore the surface of land in project areas that is disturbed during construction of the project by
(a) removing all structures not required for the operation of the facility,
(b) restoring the surface to a state that eliminates hazards, enables weed and precipitation run-off control and prevents erosion, and
(c) re-vegetating any exposed soil in accordance with section 19 (1) (d) of the Environmental Protection and Management Regulation, B.C. Reg. 200/2010.
(2) Work required by subsection (1) must be
(a) carried out during construction of the project, to the extent practicable given weather, ground and other conditions, and
(b) completed as soon as practicable after construction of the project, if the work could not practicably be completed during construction.
Read the Renewable Energy Projects Regulation on BC Laws ↗
Made under Energy Resource Activities Act, SBC 2008, c. 36.