Renewable Energy Projects Regulation, B.C. Reg. 28/2026

Section 37

Emergency response and notification

Cite as Renewable Energy Projects Regulation, B.C. Reg. 28/2026, s. 37 · last amended September 14, 2026 · read from BC Laws on November 17, 2026

The text

(1) If an emergency occurs, a permit holder for a renewable energy project must (a) immediately respond to the emergency in accordance with the emergency response plan for the project, (b) notify the regulator within one hour after becoming aware of the emergency, and (c) notify the local first nations, if any, for the hazard planning zones affected by an emergency as soon as possible after the permit holder has taken any immediate actions necessary (i) for public safety, or (ii) to minimize immediate environmental impacts. (2) A permit holder for a renewable energy project must notify the regulator within 24 hours after becoming aware of (a) an incident classified under section 36 as a minor incident, or (b) an unplanned shutdown of the facility.
Read the Renewable Energy Projects Regulation on BC Laws ↗

Made under Energy Resource Activities Act, SBC 2008, c. 36.