Renewable Energy Projects Regulation, B.C. Reg. 28/2026

Section 17

Access management plan

Cite as Renewable Energy Projects Regulation, B.C. Reg. 28/2026, s. 17 · last amended September 14, 2026 · read from BC Laws on November 17, 2026

The text

(1) A permit holder for a renewable energy project must have an access management plan that describes (a) how access will be managed within the project areas, having regard to (i) public safety, (ii) rights and interests of first nations, and (iii) government's environmental objectives, and (b) any agreements with or expectations respecting other users of land within the project areas. (2) A plan under subsection (1) must (a) be informed by the best available Indigenous knowledge, and (b) prioritize physical security of the project during construction and operation.
Read the Renewable Energy Projects Regulation on BC Laws ↗

Made under Energy Resource Activities Act, SBC 2008, c. 36.