Renewable Energy Projects Regulation, B.C. Reg. 28/2026
Section 13.1
Definitions
Cite as Renewable Energy Projects Regulation, B.C. Reg. 28/2026, s. 13.1 · last amended September 14, 2026 · read from BC Laws on November 17, 2026
The text
In this Division:
“class A project” means a renewable energy project with a rated nameplate capacity greater than 5 MW and less than 50 MW, other than a class C project;
“class B project” means a renewable energy project with a rated nameplate capacity greater than or equal to 50 MW, other than a class C project;
“class C project” means a renewable energy project that is a non-exempt reviewable project;
“investigative use licence”, in relation to a renewable energy project, means a licence of occupation under the Land Act that is issued before an application for a permit or authorizations for the project;
“major amendment” means an amendment to a permit for a renewable energy project to do one or more of the following:
(a) increase the rated nameplate capacity of the project;
(b) increase the total number of permitted wind turbines, solar arrays or battery or other energy storage systems;
(c) increase by one hectare or more an operating area of the permit;
(d) in the case of a wind energy project, increase
(i) the maximum permitted turbine height, or
(ii) the maximum permitted turbine blade size.
Read the Renewable Energy Projects Regulation on BC Laws ↗
Made under Energy Resource Activities Act, SBC 2008, c. 36.