Renewable Energy Projects Regulation, B.C. Reg. 28/2026
Section 10
Pre-engagement with first nations
Cite as Renewable Energy Projects Regulation, B.C. Reg. 28/2026, s. 10 · last amended September 14, 2026 · read from BC Laws on November 17, 2026
The text
An applicant for a permit for a renewable energy project must, before submitting an application for the project, engage local first nations about the project and prepare a report that includes the following:
(a) a description of the process used to engage local first nations;
(b) the concerns, if any, raised by the local first nations and a description of the revisions, if any, that will be made to the project based on those concerns;
(c) whether Indigenous knowledge was sought during engagement and, if so, whether
(i) that knowledge was provided, and
(ii) any knowledge that was provided was used in preparing the reports and plans required by the following sections:
(A) section 12 [adverse impacts report];
(B) section 13 [social and economic impacts report];
(C) section 16 [first nations' cultural heritage plan];
(D) section 17 [access management plan].
Read the Renewable Energy Projects Regulation on BC Laws ↗
Made under Energy Resource Activities Act, SBC 2008, c. 36.