Drilling and Production Regulation, B.C. Reg. 282/2010
Section 79
Obligations on cancellation or cessation of operations
Cite as Drilling and Production Regulation, B.C. Reg. 282/2010, s. 79 · last amended April 1, 2025 · read from BC Laws on November 17, 2026
The text
(0.1) In this section, “inactive facility” means a facility at which no petroleum, natural gas, water or substance referred to in paragraph (d) or (e) of the definition of "pipeline" in the Act is gathered, processed, measured or disposed of.
(1) The removal of the facility from the facility site is prescribed with respect to a facility permit for the purposes of section 40 (e) of the Act.
(2) The facility permit holder of an inactive facility must
(a) within 12 consecutive months of the facility becoming an inactive facility, suspend the facility in a manner that ensures its ongoing safety and integrity, and
(b) within 60 days of the suspension of the facility, notify the regulator of the suspension.
(3) A facility permit holder who has suspended operations at the facility must notify the regulator at least 5 days before reactivating the facility.
Read the Drilling and Production Regulation on BC Laws ↗
Made under Energy Resource Activities Act, SBC 2008, c. 36.