Drilling and Production Regulation, B.C. Reg. 282/2010
Section 76
Notification
Cite as Drilling and Production Regulation, B.C. Reg. 282/2010, s. 76 · last amended April 1, 2025 · read from BC Laws on November 17, 2026
The text
A facility permit holder must notify the regulator
(a) at least 2 days before beginning construction of a facility or beginning permitted modifications to a facility,
(b) at least 2 days before conducting a pressure test on process piping at a facility,
(c) at least one day before beginning production operations at a facility, and
(d) at least one day before putting new or modified equipment in service at a facility.
Read the Drilling and Production Regulation on BC Laws ↗
Made under Energy Resource Activities Act, SBC 2008, c. 36.