Drilling and Production Regulation, B.C. Reg. 282/2010
Section 52.04
Compressors
Cite as Drilling and Production Regulation, B.C. Reg. 282/2010, s. 52.04 · last amended April 1, 2025 · read from BC Laws on November 17, 2026
The text
(1) In this section:
“average vent gas rate”, in relation to a fleet of reciprocating compressors, means the rate calculated in accordance with the following formula: Σni=1 viΣni=1 (ti * ci) where n = the number of reciprocating compressors in the fleet; v = the vent gas volume, in m3, for the calendar year for each reciprocating compressor; t = the number of hours per calendar year that each reciprocating compressor is pressurized; c = the number of pressurized throws for each reciprocating compressor;
“fleet of reciprocating compressors”, in relation to a facility permit holder, means all of the following reciprocating compressors used at facilities of the facility permit holder, whether or not under the same permit:
(a) reciprocating compressors that
(i) are rated at 75 kW or more,
(ii) are pressurized for 450 hours or more per year, and
(iii) were installed before January 1, 2021;
(b) reciprocating compressors that
(i) have fewer than 4 throws,
(ii) are rated at 75 kW or more,
(iii) are pressurized for 450 hours or more per year, and
(iv) were installed on or after January 1, 2021.
(2) Subject to subsection (2.1), a facility permit holder of a facility that uses a reciprocating compressor described in paragraph (a) or (b) in the definition of "fleet of reciprocating compressors" in subsection (1) or a centrifugal compressor described in subsection (8) must, at least once each calendar year, measure the volume of natural gas emitted from each compressor seal during a 15-minute period that is representative of the normal operating conditions of the compressor.
(2.1) Subsection (2) does not apply to reciprocating compressors or centrifugal compressors if emissions of natural gas from the compressor seals
(a) are routed to hydrocarbon gas conservation equipment, or
(b) subject to sections 42 to 44, are flared.
(3) A facility permit holder of a facility that uses a reciprocating compressor described in subsection (4) or (4.1) must not vent natural gas from the compressor seals of the reciprocating compressor unless it is permitted under section 52.021.
(4) Subsection (3) applies in relation to a reciprocating compressor that
(a) has 4 or more throws,
(b) is rated at 75 kW or more,
(c) is pressurized for 450 hours or more per year, and
(d) was installed on or after January 1, 2021.
(4.1) Subsection (3) applies to a reciprocating compressor at a facility if the facility permit holder
(a) applied for a facility permit on or after January 1, 2025, or
(b) made a modification to the facility after January 1, 2028.
(5) A facility permit holder who uses a fleet of reciprocating compressors must ensure that
(a) the venting of seal gas from each throw does not exceed 3 m3 per hour, and
(b) the average vent gas rate for the fleet for each calendar year does not exceed 0.3 m3 per hour per throw.
(6) A facility permit holder who uses a fleet of reciprocating compressors must
(a) maintain a record of the average vent gas rate for the fleet for each calendar year, and
(b) submit the record to the regulator by March 31 of the calendar year after the calendar year to which the record relates.
(7) A facility permit holder who uses a fleet of reciprocating compressors must maintain, for at least 7 years from the date a record is submitted under subsection (6) (b), records of the following information for each reciprocating compressor within the fleet:
(a) the facility identification number provided to the permit holder by the regulator;
(b) a unique compressor identifier;
(c) the compressor power rating, in kW;
(d) the date the compressor was installed;
(e) the number of throws;
(f) the number of hours the compressor was pressurized;
(g) the date each compressor seal was tested;
(h) the equipment used for each compressor seal test;
(i) equipment calibration records for the equipment used;
(j) the date each compressor seal was installed;
(k) the results of each compressor seal test by volume, in m3, of natural gas emissions.
(8) A facility permit holder of a facility that uses a centrifugal compressor that is rated at 75 kw or more and is pressurized for 450 hours or more per year must ensure that the vent gas rate for the compressor is lower than the following:
(a) if the compressor was installed before January 1, 2021, 10.20 m3 per hour per compressor body;
(b) if the compressor was installed on or after January 1, 2021, 3.40 m3 per hour per compressor body.
(8.1) A facility permit holder of a facility to which this subsection applies must not vent natural gas from the seals of a centrifugal compressor unless it is permitted under section 52.021.
(8.2) Subsection (8.1) applies to a facility if the facility permit holder
(a) applied for a facility permit on or after January 1, 2025, or
(b) made a modification to the facility after January 1, 2028.
(9) A facility permit holder of a facility that uses a centrifugal compressor described in subsection (8) must
(a) prepare a compressor seal test report for the compressor each calendar year, and
(b) submit the report to the regulator by March 31 of the calendar year after the calendar year to which the report relates.
(10) A compressor seal test report under subsection (9) must include the following information:
(a) the facility identification number provided to the permit holder by the regulator;
(b) a unique compressor identifier;
(c) the number of compressor bodies;
(d) whether each seal type is wet or dry;
(e) the results of each compressor seal test by volume, in m3, of natural gas emissions.
(11) A facility permit holder of a facility that uses a centrifugal compressor described in subsection (8) must maintain, for at least 7 years from the date a compressor seal test report is submitted under subsection (9) (b), records respecting the information included in the report, including, without limitation, the following:
(a) the date each compressor seal was tested;
(b) the equipment used for each compressor seal test;
(c) equipment calibration records for the equipment used;
(d) the date each compressor seal was installed.
(12) This subsection and subsections (1) to (11) are repealed on December 31, 2034.
(13) Beginning on January 1, 2035, a facility permit holder must not vent natural gas from the compressor seals of a reciprocating compressor or the compressor seals of a centrifugal compressor unless it is permitted under section 52.021.