Pipeline Regulation, B.C. Reg. 281/2010
Section 9
Deactivation
Cite as Pipeline Regulation, B.C. Reg. 281/2010, s. 9 · last amended April 1, 2025 · read from BC Laws on November 17, 2026
The text
(1) This section applies if, for a period of 18 consecutive calendar months, a pipeline permit holder does not transport fluids through the holder's permitted pipeline or part of the pipeline.
(2) The period referred to in subsection (1) begins, as applicable,
(a) the day after the last day fluid is transported through the permitted pipeline or part of the pipeline, if the pipeline or part has been used to transport fluids, or
(b) the day after construction of the permitted pipeline or part of the pipeline is completed, if the pipeline or part has not been used to transport fluids.
(3) Before the expiry of the period referred to in subsection (1), the pipeline permit holder must do one of the following:
(a) deactivate the permitted pipeline or part of the pipeline and notify the regulator on completion of the deactivation;
(b) submit to the regulator a plan to deactivate the permitted pipeline or part of the pipeline after the end of that period;
(c) submit to the regulator a plan for resuming or beginning, as applicable, the transportation of fluids through the permitted pipeline or part of the pipeline.
(4) If a plan is submitted to the regulator under subsection (3) (b) or (c),
(a) the plan must be approved by the regulator, and
(b) the pipeline permit holder must implement the plan as approved by the regulator.
Read the Pipeline Regulation on BC Laws ↗
Made under Energy Resource Activities Act, SBC 2008, c. 36.