Hydrogen Facility Regulation, B.C. Reg. 27/2025

Section 18

Pre-operation testing

Cite as Hydrogen Facility Regulation, B.C. Reg. 27/2025, s. 18 · last amended March 10, 2026 · read from BC Laws on November 17, 2026

The text

Before operation of any part of a hydrogen facility begins, the hydrogen facility permit holder must do all of the following: (a) inspect and test (i) components and systems in accordance with the design and the requirements of the codes and standards, (ii) control devices and systems and safety critical devices to verify that the devices and systems are operating in accordance with the design, and (iii) fire suppression systems, if any; (b) conduct leak tests of equipment and piping systems; (c) conduct any other inspections or tests reasonably necessary to ensure that the facility is safe to operate; (d) submit to the regulator a statement by the qualified professional of record, in the form and manner required by the regulator, that (i) the facility was designed, constructed, inspected and tested in compliance with the codes and standards and applicable regulations, and (ii) all equipment at the facility has been verified to be safe for operation.
Read the Hydrogen Facility Regulation on BC Laws ↗

Made under Energy Resource Activities Act, SBC 2008, c. 36.