Code of Practice for Industrial Non-Hazardous Waste Landfills Incidental to the Wood Processing Industry, B.C. Reg. 263/2010

Section 15

Final closure plan

Cite as Code of Practice for Industrial Non-Hazardous Waste Landfills Incidental to the Wood Processing Industry, B.C. Reg. 263/2010, s. 15 · last amended February 18, 2022 · read from BC Laws on November 17, 2026

The text

(1) The operator of a landfill facility must, at least 3 months before the intended closure of a landfill facility, (a) notify a director in writing of the closure, and (b) make available to the director a copy of the final closure plan for the landfill facility. (2) The final closure plan must be prepared by a qualified professional. (3) Before the final closure plan is prepared, the operator of a landfill facility must ensure that a qualified professional (a) reviews the conceptual closure plan for the landfill facility, and (b) if necessary, amends the conceptual closure plan to reflect any changes in the information provided in it arising, after the preparation or amendment of the conceptual closure plan, from the operation of the landfill facility or from site specific conditions. (4) The final closure plan for a landfill facility (a) must (i) specify the final design elevation of the landfill, (ii) specify the area of the landfill, (iii) identify the measures to be taken to prevent, or minimize the risk of, (A) leachate or waste escaping from the landfill, (B) erosion of the landfill cover, (C) fire occurring in the closed landfill or its cover, or (D) water running onto the closed landfill, and (iv) identify maximum periods following the final discharge of waste before the implementation of the closure plan is initiated, and (b) include the following information relating to the landfill facility: (i) a description of the final cover of the landfill; (ii) an estimate of the total volume of solid waste discharged to the landfill; (iii) a survey of the location of the landfill, prepared by a land surveyor admitted as a land surveyor under the Land Surveyors Act; (iv) a description of how the operator of the landfill facility has managed (A) drainage restoration, (B) soil replacement, (C) the slope of the final cover, (D) erosion control, and (E) re-vegetation and conditioning of the site; (v) a description of how the operator of the landfill facility will monitor the site of the landfill facility. (5) Subject to subsection (6), the final closure plan may not be implemented until it is approved by the director. (6) The final closure plan may be implemented after the date that is 45 days after the date the operator of a landfill facility makes available to the director a copy of the final closure plan under subsection (1) (b), unless the director notifies the operator that the director does not approve the plan.
Read the Code of Practice for Industrial Non-Hazardous Waste Landfills Incidental to the Wood Processing Industry on BC Laws ↗

Made under Environmental Management Act, SBC 2003, c. 53.