Emission Offset Project Regulation, B.C. Reg. 250/2015
Section 19
Revision of project plan
Cite as Emission Offset Project Regulation, B.C. Reg. 250/2015, s. 19 · last amended July 8, 2024 · read from BC Laws on November 17, 2026
The text
(1) A proponent of an accepted emission offset project may apply to the director for an amendment to the project plan, other than to the crediting period, by submitting to the director
(a) an amended project plan,
(b) a description of and explanation for the requested amendment,
(c) an assessment of whether
(i) the amendment is consistent with the protocol under which the project was validated, and
(ii) there has been a change in an enactment of British Columbia, or Canada, or in other circumstances, affecting the project's baseline scenario, and
(d) a new validation statement and a conflict of interest report under section 16 (3)
(i) if there has been a change described in paragraph (c) (ii) that has had a material impact on the project's project reduction, or
(ii) if required by the director, in accordance with any directions given by the director.
(2) On receiving an application under subsection (1), the director may approve or reject the amendment that is the subject of the application.
(3) If under subsection (2) the director rejects an amendment, the project proponent must notify the director within the time specified by the director whether the proponent intends to carry out the project as registered.