Emission Offset Project Regulation, B.C. Reg. 250/2015
Section 17
Acceptance of project plan
Cite as Emission Offset Project Regulation, B.C. Reg. 250/2015, s. 17 · last amended July 8, 2024 · read from BC Laws on November 17, 2026
The text
(1) A validation body submitting a project plan and validation statement respecting the project plan must include the report described in section 16 (3).
(2) The director may refuse to accept a project plan in the following circumstances:
(a) the validation statement in respect of the project plan was signed more than 45 days before the date the statement is submitted to the director;
(b) the participation of the project proponent in the registry is suspended or cancelled;
(c) the project plan is inconsistent with the applicable protocol, the Act or this regulation;
(d) the validation body is under investigation by the member of the International Accreditation Forum that accredited the validation body.
Read the Emission Offset Project Regulation on BC Laws ↗
Made under Greenhouse Gas Industrial Reporting and Control Act, SBC 2014, c. 29.