(1) In this section:
“authorization” has the same meaning as in section 1 (2) of the primary Act;
“permit” has the same meaning as in section 1 (2) of the primary Act;
“specified proponent” means any of the following:
(a) in relation to the North Coast Transmission Line project, the British Columbia Hydro and Power Authority;
(b) in relation to another streamlined project, a person who holds a permit, authorization or delegated instrument for the project, whether or not issued by the regulator;
“transitional period” means the period beginning on April 1, 2024 and ending on June 30, 2026.
(2) The commissioner, for the purposes of recovering expenses arising during the transitional period out of the administration of the primary Act, as it relates to renewable energy projects, and this Act, may issue a certificate to a specified proponent requiring the specified proponent to pay an amount specified in the certificate.
(3) A certificate under subsection (2) must
(a) be served on the specified proponent, and
(b) published on a publicly available website maintained by or on behalf of the regulator.
(4) A specified proponent to whom a certificate under subsection (2) is issued must pay to the regulator the amount specified in the certificate.
(5) For certainty, the commissioner may issue more than one certificate under this section in a calendar year or in relation to a streamlined project.