Environmental Assessment Transition Regulation, B.C. Reg. 249/2019
Section 2
Transition
Cite as Environmental Assessment Transition Regulation, B.C. Reg. 249/2019, s. 2 · last amended March 26, 2020 · read from BC Laws on November 17, 2026
The text
(1) If an order under section 10 (1) (a) or (c) of the former Act has been issued with respect to a project, but an order under section 11 of the former Act has not been issued with respect to the project by the date this section comes into force, the chief executive assessment officer may not make a decision under section 18 of the Act respecting the project unless the proponent of the project has complied with sections 13 and 15 of the Act respecting the project.
(2) If an application for a determination under section 10 (1) (b) of the former Act has been made and a decision under that section has not been made before December 16, 2019, the former Act applies to that application.
Read the Environmental Assessment Transition Regulation on BC Laws ↗
Made under Environmental Assessment Act, SBC 2018, c. 51.