Direction No. 5 to the British Columbia Utilities Commission, B.C. Reg. 245/2013
Section 6
Transportation rate schedule
Cite as Direction No. 5 to the British Columbia Utilities Commission, B.C. Reg. 245/2013, s. 6 · last amended July 24, 2026 · read from BC Laws on November 17, 2026
The text
(1) Repealed. [B.C. Reg. 74/2023, s. 2 (a).]
(1.1) Within 60 days after the date this subsection comes into force, the commission must issue an order setting the transportation rate schedule as a rate for FortisBC Energy Inc., effective on the date the order is issued.
(2) In calculating rates for applicable customers, the commission must include the annual revenues and operating costs arising from services provided under the transportation rate schedule.
(3) Section 5 (2) applies to the transportation rate schedule.
(4) The commission must not exercise a power under the Act in a way that would directly or indirectly prevent FortisBC Energy Inc. from providing service under the transportation rate schedule.
(5) If the shipper is not creditworthy and has not provided the guarantee referred to in section 13.2 (b) of the transportation rate schedule, the commission must set the required security amount on the basis of the following:
(a) the shipper's creditworthiness;
(b) the contract demand and the contract term of the transportation agreement;
(c) the book value of the incremental system upgrades constructed, acquired, contracted for or secured by a utility to serve the shipper;
(d) any other matter the commission considers relevant.
(6) Terms used in subsection (5) and not defined in this direction have the same meaning as in the transportation rate schedule.
Read the Direction No. 5 to the British Columbia Utilities Commission on BC Laws ↗
Made under Utilities Commission Act, RSBC 1996, c. 473.