In considering a biomass contract under section 71 (2) of the Act, the commission may not find that a biomass contract is not in the public interest solely by reason of the factor described in section 71 (2) (d) of the Act and must be primarily guided by the following factors, which are of material value to the authority's ratepayers:
(a) the acquisition of energy by the authority under a biomass contract will reduce the risk to the authority of future costs associated with the production of gases that contribute to global climate change;
(b) energy acquired by the authority under a biomass contract will contribute to diversification of the authority's electricity supply portfolio;
(c) a biomass contract will assist the authority to meet its requirements for electrical capacity.