Reviewable Projects Regulation, B.C. Reg. 243/2019
Section 1
Definitions
Cite as Reviewable Projects Regulation, B.C. Reg. 243/2019, s. 1 · last amended December 15, 2025 · read from BC Laws on November 17, 2026
The text
In this regulation:
“Act” means the Environmental Assessment Act;
“applicable table”, in relation to a new project, a modification to an existing project or the dismantling and abandonment of an existing project, means whichever of Tables 1 to 14 lists in Column 1 the category of project within which the new or existing project fits;
“carbon dioxide equivalent” has the same meaning as in the Greenhouse Gas Industrial Reporting and Control Act;
“CWF” means the contaminant weighting factor set out in Appendix 1 for a permitted contaminant;
“existing project” means a constructed or substantially constructed project, whether operation or not, but does not include a project that has permanently ceased operations and has been abandoned;
“facility” means one or more physical works or structures that have been or will be constructed as part of a project;
“foreshore” means land in tidal or non-tidal areas that, as a result of the rise and fall of the sea or water in an estuary or stream between the natural boundary and the ordinary low water mark, is periodically covered by salt water or fresh water and periodically exposed;
“greenhouse gas” has the same meaning as in the Climate Change Accountability Act;
“NAICS code” means the code in the North American Industrial Classification System, 2017;
“natural boundary” has the same meaning as in the Land Act;
“new project” means a proposed project, or a project for which construction has begun but that has not started regular operations;
“stream” has the same meaning as in the Water Sustainability Act;
“submerged land” means land that lies below the ordinary low water mark of a stream, marine coastline or estuary and that is normally covered by salt water or fresh water;
“waste discharge” means the quantity of gaseous, liquid or solid waste contaminants introduced into the environment from a facility.
Read the Reviewable Projects Regulation on BC Laws ↗
Made under Environmental Assessment Act, SBC 2018, c. 51.