Municipalities Enabling and Validating Act (No. 5), SBC 2023, c. 3
Section 4
Notice of termination
Cite as Municipalities Enabling and Validating Act (No. 5), SBC 2023, c. 3, s. 4 · read from BC Laws on November 17, 2026
The text
(1) The regional district must give written notice of the termination of the specified land use contract to the owners of the land subject to the specified land use contract.
(2) A notice under subsection (1) must
(a) be mailed or otherwise delivered as follows:
(i) if the regional district adopts a bylaw under section 3 that will terminate the specified land use contract, by the date that is 10 days after the adoption of the bylaw to the owners as shown on the assessment roll as at the date of the first reading of the bylaw;
(ii) if subparagraph (i) does not apply, by June 30, 2032 or, if a date is prescribed under section 2 (3), by the date that is 2 years before the prescribed date to the owners as shown on the assessment roll as at a date no more than one month before the notice is mailed or delivered,
(b) identify the place where and the times and dates when zoning bylaws are available for public inspection, and
(c) if the regional district adopts a bylaw under section 3 that will terminate the specified land use contract, inform the owners that they may apply to a board of variance for an exemption under section 543 [exemption to relieve hardship from early termination of land use contract] of the Local Government Act.
(3) The obligation to deliver a notice under subsection (2) (a) is satisfied if a reasonable effort was made to mail or otherwise deliver the notice.
Read the Municipalities Enabling and Validating Act (No. 5) on BC Laws ↗