Timber Harvesting Contract and Subcontract Regulation, B.C. Reg. 22/96

Section 42

Notification to contractors for interior area or coast area

Cite as Timber Harvesting Contract and Subcontract Regulation, B.C. Reg. 22/96, s. 42 · last amended March 30, 2022 · read from BC Laws on November 17, 2026

The text

For each contract used by a licence holder for the purpose of complying with a contractor clause in a licence for the interior area or for the coast area, the licence holder must (a) provide a copy of the contract to the ministry on request, and (b) advise the contractor, on request, whether the contract is being used for the purpose of complying with the contractor clause in the licence and, if so, of the volume of timber attributed to the contract by the licence holder for the purposes of complying with the contractor clause in that licence.
Read the Timber Harvesting Contract and Subcontract Regulation on BC Laws ↗

Made under Forest Act, RSBC 1996, c. 157.