Acceptance of a proposal
Cite as Timber Harvesting Contract and Subcontract Regulation, B.C. Reg. 22/96, s. 33.41 · last amended March 30, 2022 · read from BC Laws on November 17, 2026
The text
(1) If no impacted contractor gives the licence holder written notice of an objection to a forestry revitalization proposal under section 33.4, the proposal is deemed to be accepted and each contract entered into by the licence holder with respect to the licences held by that licence holder and included in the proposal is deemed to be amended or terminated on the expiry of the 30 day period referred to in section 33.4 (1) or on a later date provided in the proposal.
(2) If a rejection threshold of contractors gives a licence holder written notice of an objection to a forestry revitalization proposal under section 33.4, and at least one of those contractors is an impacted contractor, the forestry revitalization proposal is rejected.
(3) If a forestry revitalization proposal is not rejected under subsection (2), it is deemed to be accepted.
(4) If a forestry revitalization proposal is rejected under subsection (2) or deemed to be accepted under subsection (1) or (3), the licence holder, within 7 days of the rejection or acceptance, must provide written notice of the rejection or acceptance to all contractors who received the proposal under section 33.22, which notice must list those contractors who gave written notice of objection under section 33.4.