Timber Harvesting Contract and Subcontract Regulation, B.C. Reg. 22/96
Section 23
Amount of work dispute
Cite as Timber Harvesting Contract and Subcontract Regulation, B.C. Reg. 22/96, s. 23 · last amended March 30, 2022 · read from BC Laws on November 17, 2026
The text
(1) If the parties to a replaceable contract that relates to a licence for the coastal area have not agreed upon the amount of work to be specified in the contract, and the amount has not been determined in accordance with this section, either party may provide the other with a notice in writing stating the amount of work that party believes should be specified in the contract.
(2) A contractor who receives a notice from a licence holder in accordance with subsection (1) must, within 30 days of receiving the notice
(a) advise the licence holder in writing that it agrees that the amount of work stated in the notice is the amount which should be specified in the contract, or
(b) provide a notice in writing to the licence holder stating the amount of work the contractor believes should be specified in the contract.
(3) A contractor who fails to comply with subsection (2) is deemed to have agreed with the amount of work stated in the licence holder's notice, and the replaceable contract is deemed to be amended to specify that amount of work.
(4) A licence holder who receives a notice from a contractor in accordance with subsection (1) or (2) (b) must, within 30 days of receiving the notice
(a) advise the contractor in writing that it agrees that the amount of work stated in the notice is the amount of work which should be specified in the contract, or
(b) make an amount of work proposal.
(5) A licence holder who fails to comply with subsection (4) is deemed to have agreed with the amount of work stated in the contractor's notice, and the replaceable contract is deemed to be amended to specify that amount of work.
(6) An amount of work proposal made by a licence holder under subsection (4) (b) must
(a) be made in writing,
(b) be delivered to each contractor who has a replaceable contract to which the proposal relates,
(c) describe the nature of the amount of work dispute,
(d) state the amount of work that the licence holder proposes to be specified in each replaceable contract relating to the licence,
(e) state the amount of work that the licence holder claims it has historically conducted through company operations, and
(f) state how the amount of work proposal takes into account the provisions of section 18.
(7) Repealed. [B.C. Reg. 278/2004, s. 15.]
(8) If a contractor who receives an amount of work proposal objects to the proposal, the contractor must give written notice to the licence holder within 30 days of delivery of the proposal to that contractor.
(9) If no contractor who receives an amount of work proposal objects to the proposal in accordance with subsection (8), the proposal is deemed to be accepted, and the replaceable contracts of each contractor to whom the proposal was delivered are deemed to be amended to the extent necessary to implement the proposal.
(10) If a licence holder receives a notice of objection with respect to an amount of work proposal in accordance with subsection (8), a dispute is deemed to exist with respect to each of the replaceable contracts that the proposal relates to and must be resolved by mediation and, if necessary, arbitration under the system established in Division 2 of Part 4, subject to the following:
(a) the licence holder and each contractor with a replaceable contract to carry out one or more phases of the licence holder's timber harvesting operations under the licence to which the proposal relates must be parties to the mediation and, if the mediation is not successful, to the arbitration, and any reference to "party" and "parties" in Division 2 of Part 4 must be read accordingly;
(b) the licence holder and any contractor with a replaceable contract to which the amount of work proposal relates may commence proceedings by delivering a notice of dispute as provided in section 8 (13) (b);
(c) a licence holder or any contractor with a replaceable contract to which the amount of work proposal relates who refers an amount of work proposal to mediation or arbitration must deliver a notice of the time and place of the mediation to each union whose members may be affected by the disposition of the amount of work dispute;
(d) a union that is entitled to receive notice under paragraph (c) may take part in the mediation or arbitration as an intervenor by making submissions, including making an amount of work proposal, and may take part in other ways to the extent permitted by the mediator or arbitrator;
(e) each contractor that is a party to an arbitration regarding an amount of work dispute may make an amount of work proposal;
(f) the arbitration of an amount of work dispute must be conducted by a sole arbitrator;
(g) an arbitrator must resolve a dispute regarding the amount of work to be specified in a replaceable contract having regard to the requirements of section 18;
(h) in adjudicating the dispute, an arbitrator must express the amount of work to be specified in the contract in a manner consistent with the provisions of section 18.
Read the Timber Harvesting Contract and Subcontract Regulation on BC Laws ↗