The text
(1) A licence holder may, for bona fide business and operating reasons, allocate to a contractor with a replaceable contract work that pertains to timber that the licence holder is entitled to harvest outside the licence to which the contract pertains.
(2) If a licence holder allocates work to a contractor under subsection (1),
(a) the licence holder must advise the contractor that the work is being allocated in substitution for work under the licence to which the contract pertains before the contractor commences the work,
(b) the work is deemed to be allocated under the contract and all the provisions of the contract apply to the work, and
(c) there is no obligation for the licence holder to allocate any work outside the licence to the contractor at any other time.
Read the Timber Harvesting Contract and Subcontract Regulation on BC Laws ↗