The text

(1) A replaceable contract must provide that the licence holder may allocate to the contractor and the contractor must perform, in any given year of the term of the contract, an amount of work that is less than the amount of work specified in the contract to enable the licence holder to experiment with timber harvesting methods, technology or silviculture systems different from those historically used by the licence holder on the licence to which the contract relates, provided that (a) the contractor receives reasonable notice, (b) the experiment is for bona fide business and operational reasons, (c) it is not practicable for the contractor to perform the work required to conduct the experiment, and (d) the licence holder has used reasonable efforts to fairly distribute among company operations and other contractors carrying out timber harvesting operations under the licence the reduction of work associated with any experiments. (2) In an arbitration of a dispute arising from or in relation to a reduction in the amount of work under subsection (1) the onus lies on the licence holder to establish that the conditions entitling the licence holder to reduce the amount of work have been satisfied.
Read the Timber Harvesting Contract and Subcontract Regulation on BC Laws ↗

Made under Forest Act, RSBC 1996, c. 157.