(1) A replaceable contract must specify an amount of work to be performed in each year during the term of the contract.
(2) A replaceable contract must provide that the specified amount of work to be performed in each year of the replaceable contract may not be reduced by a licence holder except as expressly provided for in the regulation or in a clause required, or permitted to be in the contract by this regulation.
(3) A replaceable contract may provide for work to be performed in relation to timber harvesting operations carried out under more than one licence.
(4) If a replaceable contract provides for work to be performed in relation to timber harvesting operations carried out under more than one licence as provided in subsection (3),
(a) the replaceable contract must specify an amount of work in respect of each licence, and
(b) the amount of work to be specified in respect of each licence must be determined separately.
(5) At the request of a contractor, a licence holder must provide information to confirm that the amount of work that is specified in the replaceable contract under subsection (1) meets the requirements of section 18 or 19.
(6) A contractor must keep confidential any information received under subsection (5), except to the extent that disclosure is required in the mediation or arbitration of an amount of work dispute.