Direction to the British Columbia Utilities Commission Respecting the North Coast Transmission Line Project, B.C. Reg. 227/2025

Section 3

North Coast industrial tariff

Cite as Direction to the British Columbia Utilities Commission Respecting the North Coast Transmission Line Project, B.C. Reg. 227/2025, s. 3 · last amended December 8, 2025 · read from BC Laws on November 17, 2026

The text

(1) Within 10 days after the date the authority files an application for the purposes of this section, the commission must issue final orders so that the Electric Tariff of the authority is amended by adding the following rates: (a) Electric Tariff Supplement No. 109 as set out in Schedule 1; (b) Electric Tariff Supplement No. 114 as set out in Schedule 2; (c) Electric Tariff Supplement No. 115 as set out in Schedule 3. (2) The commission must not cancel, suspend or amend a rate referred to in subsection (1) (a), (b) or (c).
Read the Direction to the British Columbia Utilities Commission Respecting the North Coast Transmission Line Project on BC Laws ↗

Made under Utilities Commission Act, RSBC 1996, c. 473.