Asphalt Plant Regulation, B.C. Reg. 217/97
Section 8
Location
Cite as Asphalt Plant Regulation, B.C. Reg. 217/97, s. 8 · last amended October 28, 2019 · read from BC Laws on November 17, 2026
The text
(1) The owner or operator must provide to a director, in writing, at least 14 days before commencement of a project, notification of the plan of operation which includes all of the following information:
(a) the registration information provided under section 3 (2);
(b) the start and end dates, and the daily working hours, for the project;
(c) the geographic location of the project;
(d) a contact name and the address of the client for the project;
(e) the number of square metres of pavement and the tonnes of pavement to be recycled as part of the project;
(f) a copy of the most recent stack monitoring results for the plant;
(g) for a direct fired infrared heating plant, the date of the last maintenance of the emission control equipment, if any.
(2) If an adjustment is made to the plan of operation after giving notification under subsection (1), the operator must notify the director, in writing, within 3 days after making the adjustment.
Read the Asphalt Plant Regulation on BC Laws ↗
Made under Environmental Management Act, SBC 2003, c. 53.