Emergency Management Regulation, B.C. Reg. 217/2017
Section 5
Response contingency plans
Cite as Emergency Management Regulation, B.C. Reg. 217/2017, s. 5 · last amended April 1, 2025 · read from BC Laws on November 17, 2026
The text
(1) Subject to this section, a permit holder must prepare and maintain a plan in accordance with CSA Z246.2.
(2) If both of the following conditions are met, the permit holder may prepare a single, coordinated plan for more than one of the permit holder's energy resource activities:
(a) the site-specific hazards and risks of each energy resource activity that would be the subject of a plan are the same;
(b) the same emergency response staff are assigned, in accordance with the permit holder's emergency management system, to the energy resource activities.
(3) A permit holder must prepare a plan in 2 parts so that the regulator can make one part of the plan publicly available.
(4) A permit holder must not include the following information in the part of the plan to be made publicly available:
(a) personal information, as defined in the Freedom of Information and Protection of Privacy Act;
(b) information the permit holder considers to be confidential business information.
(5) If part of the emergency planning zone for an energy resource activity is located within an airport zoning area, a plan for the energy resource activity must include contact information for the operator of the airport.
(6) A plan is prescribed for the purposes of section 38 (1) (b) of the Act.
Read the Emergency Management Regulation on BC Laws ↗