Direction No. 4 to the British Columbia Utilities Commission, B.C. Reg. 203/2013

Section 3

Rates

Cite as Direction No. 4 to the British Columbia Utilities Commission, B.C. Reg. 203/2013, s. 3 · last amended October 12, 2013 · read from BC Laws on November 17, 2026

The text

(1) In setting rates under the Act for the authority, the commission must ensure that the rates allow the authority to collect sufficient revenue in each fiscal year to enable it to recover the following costs from the following customers: (a) program costs, investigation costs and infrastructure costs from (i) applicable customers at applicable premises where a legacy meter or radio-off meter is installed, to the extent that the authority requests recovery of any of those costs from these customers, and (ii) all customers, to the extent that any of those costs are not recovered under subparagraph (i); (b) from all customers, costs incurred with respect to the installation and operation of, and services related to, smart meters; (c) failed installation costs from customers at a premises where a failed installation occurred. (2) The commission must allow the authority to establish a regulatory account for the recovery of costs referred to in subsection (1) (a) (ii) and (1) (b) for the period from January 1, 2013, to March 31, 2014. (3) Within 30 days of the date this direction comes into force, the commission must issue an order so that the Electric Tariff of the authority is amended by adding the provisions set out in the Appendix to this direction. (4) The commission must not do anything to amend the provisions added to the Electric Tariff under subsection (3), except on application by the authority.
Read the Direction No. 4 to the British Columbia Utilities Commission on BC Laws ↗

Made under Utilities Commission Act, RSBC 1996, c. 473.