Spill Contingency Planning Regulation, B.C. Reg. 186/2017

Section 14

Reviewing and updating spill contingency plan

Cite as Spill Contingency Planning Regulation, B.C. Reg. 186/2017, s. 14 · last amended September 1, 2023 · read from BC Laws on November 17, 2026

The text

(1) For the purposes of section 91.11 (1) (b) [regulated persons — spill contingency planning] of the Act, a regulated person who has a spill contingency plan must, at the frequency required by subsection (2) of this section, review the plan and make updates, if necessary, to (a) correct deficiencies in the plan, or (b) adjust the plan to reflect changed circumstances. (2) The regulated person must review and update the spill contingency plan (a) at least once each calendar year, and (b) within one month after any of the following events occur: (i) a change in the regulated substances, or the quantities of the regulated substances, transported by the regulated person that could result in a material increase to the magnitude of the risk referred to in section 91.11 (2) of the Act; (ii) a vacancy in one of the jobs that is noted by title in the plan for the purposes of section 7 (1) (a) or (2) (a) [incident command system]; (iii) spill response equipment noted in the plan is no longer available.
Read the Spill Contingency Planning Regulation on BC Laws ↗

Made under Environmental Management Act, SBC 2003, c. 53.