Environmental Assessment Act, SBC 2018, c. 51
Section 17
Minister's decision whether to terminate or exempt a project
Cite as Environmental Assessment Act, SBC 2018, c. 51, s. 17 · read from BC Laws on November 17, 2026
The text
(1) Subject to subsection (2), on receiving a referral and recommendation under section 16, the minister may
(a) subject to subsection (3), order that the project may not proceed as proposed,
(b) order that the proponent is exempt from the requirement under section 6 to obtain an environmental assessment certificate for the project, or
(c) refer the project to the chief executive assessment officer for a further decision under section 16.
(2) In making a decision under subsection (1), the minister must consider the sustainability purpose referred to in section 2 (2) (b) (i), the reconciliation purpose referred to in section 2 (2) (b) (ii) and the prescribed matters, if any.
(3) Before issuing an order under subsection (1) (a), the minister must give the proponent an opportunity to be heard.
(4) The minister may attach to an order under subsection (1) (a) or (b) conditions that the minister considers necessary.
(5) An order under subsection (1) (a) or (b) does not relieve the proponent from compliance with the applicable requirements that pertain to the project under other enactments.
(6) An order under subsection (1) (a) or (b) must set out the reasons for the order and must, in a case where a notification referred to in section 16 (4) (b) or (5) (b) indicates a lack of consent to the issuance of the order, give reasons for why the decision to issue the order was made.