Environmental Assessment Act, SBC 2018, c. 51
Section 10
Project notifications
Cite as Environmental Assessment Act, SBC 2018, c. 51, s. 10 · read from BC Laws on November 17, 2026
The text
(1) A person who proposes a project that is not a reviewable project under the regulations under section 9 but is within a prescribed category of projects must, within the prescribed period, submit to the chief executive assessment officer a project notification.
(2) A project notification must include
(a) the prescribed information, and
(b) any other information the chief executive assessment officer requires.
(3) A person referred to in subsection (1) must not
(a) undertake or carry on any activity that is the project referred to in the project notification, or
(b) construct, operate, modify, dismantle or abandon all or part of the facilities of the project referred to in the project notification
unless one of the following has occurred:
(c) the person has been notified under subsection (4) (c) that no further review of the project under this section is required;
(d) any review of the project that is required has been completed.
(4) Within 60 days of receiving a project notification, the chief executive assessment officer must do one of the following:
(a) submit the project notification to the minister for consideration under section 11 and provide notice to the person who proposes the project that the project notification has been submitted to the minister for that purpose;
(b) provide notice to the person who proposes the project that further review of the project under this section is required;
(c) provide notice to the person who proposes the project that no further review of the project under this section is required.
(5) A notice provided under subsection (4) (b) may include
(a) procedures and consultations respecting the project that must be carried out by the person who proposes the project, and
(b) instructions respecting the submission of a revised project notification once the procedures and consultations referred to in paragraph (a) have been carried out.