Direction respecting capital costs

Cite as Direction to the British Columbia Utilities Commission Respecting Load Attraction and Low-Carbon Electrification, B.C. Reg. 156/2022, s. 5 · last amended June 27, 2022 · read from BC Laws on November 17, 2026

The text

The commission must not disallow for any reason the recovery in rates from persons who receive or may receive service under the specified rate schedules, over a period determined by the authority, of the capital costs incurred by the authority to provide service to persons who receive incentives or other funding, or are otherwise encouraged to apply for service, under the load-attraction program or the low-carbon electrification program.
Read the Direction to the British Columbia Utilities Commission Respecting Load Attraction and Low-Carbon Electrification on BC Laws ↗

Made under Utilities Commission Act, RSBC 1996, c. 473.