Direction to the British Columbia Utilities Commission Respecting Load Attraction and Low-Carbon Electrification, B.C. Reg. 156/2022
Section 3
Direction respecting load attraction
Cite as Direction to the British Columbia Utilities Commission Respecting Load Attraction and Low-Carbon Electrification, B.C. Reg. 156/2022, s. 3 · last amended June 27, 2022 · read from BC Laws on November 17, 2026
The text
(1) The commission must allow the authority to establish a load-attraction costs regulatory account.
(2) The commission must allow the authority to defer to the load-attraction costs regulatory account
(a) up to $52 million in costs incurred by the authority during the period beginning April 1, 2022 and ending March 31, 2027 to provide the load-attraction program, and
(b) interest on the balance in the account.
(3) The commission must allow the authority to amortize from the load-attraction costs regulatory account for each fiscal year the forecast
(a) interest on the balance in the account, and
(b) annual load-attraction amortization amount, calculated on the assumption that the costs to provide the load-attraction program for the fiscal year will be amortized over a period of 20 years.
(4) In setting rates for the authority for a fiscal year, the commission must not disallow for any reason the recovery in rates from persons who receive or may receive service under the specified rate schedules of the forecast amounts amortized under subsection (3) (a) and (b) for the fiscal year.
(5) In setting rates for the authority for a test period, the commission must not disallow for any reason
(a) the recovery in rates from persons who receive or may receive service under the specified rate schedules of the amount, if any, by which actual amounts described in subsection (3) (a) and (b) for the previous test period exceed the forecast amounts under that subsection for that period, or
(b) the refunding in rates to persons who receive or may receive service under the specified rate schedules of the amount, if any, by which the actual amounts described in subsection (3) (a) and (b) for the previous test period are less than the forecast amounts under that subsection for that period.
(6) For the purposes of this section, interest is to be calculated for each fiscal year at the rate equal to the authority's weighted average cost of debt for the fiscal year.
(7) Except on application by the authority, the commission must not order the authority to close the load-attraction costs regulatory account.
Read the Direction to the British Columbia Utilities Commission Respecting Load Attraction and Low-Carbon Electrification on BC Laws ↗
Made under Utilities Commission Act, RSBC 1996, c. 473.