(1) Subject to subsections (2) to (4) and section 9, with the approval of the Lieutenant Governor in Council, the minister may, on behalf of the government, enter into an LNG project agreement under which the government provides to a person an indemnity respecting
(a) the amount of additional tax paid by the person in the event of a tax law change, and
(b) the person's direct costs of complying with a greenhouse gas regulatory change.
(2) An LNG project agreement must
(a) include a provision that the indemnity is conditional on the minister being satisfied that a final investment decision has been made respecting the LNG facility,
(b) be in respect of only one LNG facility,
(c) include provisions
(i) establishing a threshold that applies for losses or expenditures attributable to tax law changes and greenhouse gas regulatory changes, and
(ii) providing that the indemnity referred to in subsection (1) does not apply in relation to losses or expenditures that are less than the threshold,
(d) provide that the agreement is governed by the laws of British Columbia,
(e) provide that the venue for any proceeding to resolve a dispute arising out of or related to the agreement must be in British Columbia,
(f) include a provision for determining the date when the LNG facility is to be considered, for the purposes of subsection (3), to begin commercial operations, which date must not be later than the date of the first departure of LNG in commercial quantities from the LNG facility, and
(g) include a provision that the government's financial obligation in relation to the agreement is limited solely to the indemnity referred to in subsection (1).
(3) An LNG project agreement may not be for a term that ends later than 25 years after the later of the following:
(a) the effective date of the agreement;
(b) the date the applicable LNG facility begins commercial operations.
(4) An LNG project agreement entered into under subsection (1) may include any other terms, conditions or limitations that the minister considers necessary or advisable, including terms limiting the applicability of the indemnity referred to in that subsection further than the applicability is limited by the definition in section 1 of "carbon tax change", "greenhouse gas regulatory change", "LNG tax change" or "natural gas tax credit change", as applicable.
(5) For certainty, subsection (4) does not authorize the minister to provide, in an LNG project agreement, an indemnity respecting payments made or costs incurred as a result of
(a) an amendment or enactment not identified in the definition in section 1 of "carbon tax change", "greenhouse gas regulatory change", "LNG tax change" or "natural gas tax credit change", or
(b) the creation, modification or termination of any program other than an incentive program.