Forest Planning and Practices Regulation, B.C. Reg. 14/2004

Section 77

Retaining information

Cite as Forest Planning and Practices Regulation, B.C. Reg. 14/2004, s. 77 · last amended January 1, 2026 · read from BC Laws on November 17, 2026

The text

(1) A person who builds a bridge or major culvert for the purpose of constructing or maintaining a road must do all of the following: (a) prepare or obtain (i) pile driving records, (ii) for new materials used to build the bridge or major culvert, mill test certificates, in-plant steel fabrication drawings, and concrete test results, (iii) soil compaction results, and (iv) other relevant field and construction data; (b) prepare as-built drawings of the bridge or major culvert; (c) retain the information referred to in paragraphs (a) and (b) until the earlier of the date that (i) the bridge or major culvert is removed, and (ii) the person is no longer required to maintain the road. (2) Subject to subsection (3), a person responsible for maintaining a road must retain a copy of inspection records for a bridge or major culvert associated with the road for at least one year after the bridge or major culvert is removed from the site. (3) Unless the road has been deactivated, a person must submit to the minister or the timber sales manager, as applicable, the documents, drawings and records described in subsections (1) and (2) in respect of a road if the person is no longer required to maintain the road because the minister or timber sales manager (a) cancelled the road permit, road use permit or special use permit for the road, and (b) does not require the road to be deactivated.
Read the Forest Planning and Practices Regulation on BC Laws ↗

Made under Forest and Range Practices Act, SBC 2002, c. 69.