Liquefied Natural Gas Facility Regulation, B.C. Reg. 146/2014
Section 9
Pre-operation testing
Cite as Liquefied Natural Gas Facility Regulation, B.C. Reg. 146/2014, s. 9 · last amended April 1, 2025 · read from BC Laws on November 17, 2026
The text
(1) Before beginning operation of any portion of an LNG facility, an LNG facility permit holder must do all of the following inspections and tests:
(a) test the components and systems of the facility
(i) in accordance with CSA Z276, or
(ii) in a manner consistent with the design standard used in a quantitative risk assessment undertaken under section 4 (4), if applicable;
(b) inspect and test all control and safety devices and systems to ensure that the devices and systems are operating properly;
(c) conduct any applicable tests of LNG containment system integrity;
(d) test any applicable fire-water system;
(e) any other inspections or tests reasonably necessary to ensure that the LNG facility is safe to operate.
(2) An LNG facility permit holder must notify the regulator at least 7 days before beginning a test referred to in subsection (1) (b) to (e).
(3) An LNG facility permit holder must provide to the regulator the results of the tests referred to in subsection (1) (c) and (d) as soon as practicable after carrying out the tests.
(4) An LNG facility permit holder must not begin operation of any portion of an LNG facility unless the results submitted under subsection (3) are satisfactory to the regulator.
Read the Liquefied Natural Gas Facility Regulation on BC Laws ↗
Made under Energy Resource Activities Act, SBC 2008, c. 36.