Liquefied Natural Gas Facility Regulation, B.C. Reg. 146/2014
Section 7
Site restoration after construction
Cite as Liquefied Natural Gas Facility Regulation, B.C. Reg. 146/2014, s. 7 · last amended April 1, 2025 · read from BC Laws on November 17, 2026
The text
(1) An LNG facility permit holder must, in accordance with subsection (2), restore the surface of the land disturbed by the construction of an LNG facility not required for the safe and efficient operation of the LNG facility by
(a) removing all structures installed to facilitate construction and not required for the operation of the LNG facility, and
(b) stabilizing, contouring, conditioning or reconstructing the surface of the land to the extent reasonable in the circumstances.
(2) Restoration work under subsection (1) must be carried out
(a) to the extent practicable, considering weather, ground and other conditions, while construction of the LNG facility is underway, and
(b) with respect to any restoration work not completed when construction of the LNG facility is completed, as soon as practicable after beginning operation of the LNG facility.
Read the Liquefied Natural Gas Facility Regulation on BC Laws ↗
Made under Energy Resource Activities Act, SBC 2008, c. 36.