Water Sustainability Act, SBC 2014, c. 15
Section 93
Powers of engineers and officers
Cite as Water Sustainability Act, SBC 2014, c. 15, s. 93 · read from BC Laws on November 17, 2026
The text
(1) An order under this section may be directed to any person who has a right, permission or obligation under this Act, including, without limitation,
(a) in the case of works in respect of which an authorization, change approval, permit or drilling authorization is required, to a person who holds the authorization, change approval, permit or drilling authorization, as applicable, authorizing the construction or use of the works,
(b) in the case of works for which no authorization, change approval, permit or drilling authorization is required, to a person who constructs or installs the works, owns the works or is the owner of the land on which the works are located,
(c) in the case of the diversion or use of water under an authorization or change approval, to a person who holds the authorization or change approval,
(d) in the case of the diversion or use of water other than under an authorization or change approval, to the person who is diverting or using the water without an authorization or change approval, whether or not an authorization or change approval is required,
(e) in the case of works for which an authorization, change approval, permit or drilling authorization is required but has not been obtained, to the person who has constructed or is using the works,
(f) in relation to changes in and about a stream, to the person who made the changes in and about a stream or a person who derives a benefit from those changes in and about a stream, and
(g) in relation to a matter respecting groundwater or a well, to a person responsible within the meaning of section 48 [definitions for Division 3 of Part 3].
(2) In addition to the other powers given under this Act, for the purpose of enforcing the provisions of this Act, the regulations or the terms and conditions of an authorization, change approval, permit, drilling authorization or compliance agreement, or administering precedence of rights in relation to the diversion or use of water, an engineer may do one or more of the following:
(a) inspect, take action, close or lock works;
(b) inspect or take action in relation to the construction of works;
(c) determine whether water is being beneficially used;
(d) order the construction, alteration, installation, replacement, repair, maintenance, improvement, sealing, deactivation, decommissioning or removal of any works;
(e) order
(i) a person who makes changes in and about a stream or any person who derives a benefit from the changes in and about a stream to restore or remediate those changes, or
(ii) if the engineer considers that the impacts of changes in and about a stream made by that person cannot be remediated, or cannot be fully remediated, at the location of the changes in and about the stream, compensatory mitigation measures, in place of or supplemental to other remediation measures, on a different part of the stream in respect of which changes were made, or with the consent of the person, on another stream;
(f) order the construction, installation and maintenance of a measuring or testing device in addition to any construction, installation or maintenance of measuring or testing devices required under the regulations;
(g) order the operation of, and provision of data from, a measuring or testing device in addition to any operation or provision of data required under the regulations;
(h) order a person who is not subject to the regulations in relation to the measuring, testing or reporting under section 131 [regulations respecting measuring, testing and reporting] to comply with specified regulations or to otherwise measure, test and report in relation to water usage or works;
(i) in person or through an officer or a water bailiff, make orders and take action with respect to the diversion, rate of diversion, time of diversion, carriage, distribution and use, including storage and time of storage, of water;
(j) in accordance with directions of the comptroller or a water manager, give directions, in person or through an officer, to a water bailiff to
(i) take action respecting the diversion, rate of diversion, time of diversion, carriage, distribution or use, including storage and time of storage, of water from the streams and aquifers specified in the water bailiff's appointment,
(ii) take action respecting works related to the activities referred to in subparagraph (i), and
(iii) take measures to carry out the operation, routine repair or maintenance of works;
(k) order the release of stored or impounded water that the engineer considers to be a danger to public safety or property;
(l) order the owner of a flowing artesian well, or if the owner of the well is not known, the owner of the land on which the well is situated, to engage a well driller who is qualified in respect of the activity or a professional, as defined in section 48 [definitions for Division 3 of Part 3], to ensure that the artesian flow of that well is stopped or brought under control in accordance with section 53 [controlling flowing artesian well];
(m) order a change in the operation of a well that is being operated contrary to section 58 [well operation] and give directions respecting the operation of the well;
(n) order a person to remediate or mitigate any impact on an aquifer, groundwater or the existing uses of groundwater that results because a well was sited, constructed, floodproofed or operated other than in accordance with the requirements of this Act or the regulations;
(o) install measuring or testing devices;
(p) take measurements of or test
(i) water in a stream or aquifer,
(ii) the flow of water in a stream or aquifer, or
(iii) works;
(q) determine the allowances of water to offset evaporation, seepage and other losses.
(3) An order under subsection (2) may be made subject to any terms and conditions the engineer considers advisable.
(4) In accordance with directions of an engineer, an officer may do one or more of the following:
(a) take action, close or lock works;
(b) take action in relation to the construction of works;
(c) install measuring or testing devices;
(d) take measurements of or test
(i) water in a stream or aquifer,
(ii) the flow of water in a stream or aquifer, or
(iii) works;
(e) in person or through a water bailiff, take action with respect to the diversion, rate of diversion, time of diversion, carriage, distribution and use, including storage and time of storage, of water;
(f) take action respecting works related to the activities referred to in paragraph (e), or direct a water bailiff to do so;
(g) direct a water bailiff to take measures to carry out the operation, routine repair or maintenance of those works.
(5) An officer may inspect
(a) works,
(b) the construction, deactivation or decommissioning of works,
(c) an existing or proposed water use,
(d) an activity or changes in and about a stream, and
(e) records related to a matter referred to in paragraphs (a) to (d).
(6) For the purposes of section 94 (8), an engineer or officer may examine the works authorized under an authorization, change approval, permit or drilling authorization or the place of use referred to in an authorization, change approval, permit or drilling authorization and make a finding referred to in that section.