Water Sustainability Act, SBC 2014, c. 15

Section 45

No new dams on protected rivers

Cite as Water Sustainability Act, SBC 2014, c. 15, s. 45 · read from BC Laws on November 17, 2026

The text

(1) A person must not construct a bank-to-bank dam anywhere on a protected river. (2) The comptroller or a water manager must not issue or amend an authorization, change approval or permit to authorize the construction of a bank-to-bank dam anywhere on a protected river. (3) An authorization, change approval or permit issued or an amendment made contrary to subsection (2) has no effect. (4) This section applies despite any other enactment. (5) This section does not apply to a dam authorized by a licence, permit or approval issued under the Water Act before March 15, 1997.
Read the Water Sustainability Act on BC Laws ↗