Water Sustainability Act, SBC 2014, c. 15
Section 26
Amendment or substitution of authorization, change approval or permit
Cite as Water Sustainability Act, SBC 2014, c. 15, s. 26 · read from BC Laws on November 17, 2026
The text
(1) On application by the holder in accordance with section 12 [application and decision maker initiative procedures], or on the comptroller's or water manager's own initiative, the comptroller or a water manager may amend an authorization and a permit issued in relation to the authorization, and the comptroller, a water manager or an engineer may amend a change approval and a permit issued in relation to the change approval, to do any of the following:
(a) extend the time set for beginning construction of works;
(b) extend the time set for completion of works;
(c) extend the time set for making beneficial use of water;
(d) authorize additional or other works than those previously authorized;
(e) correct an error in the authorization, change approval or related permit;
(f) remove a provision of the authorization, change approval or related permit that is inconsistent with this Act;
(g) authorize the use of water for a water use purpose other than a water use purpose specified in the authorization;
(h) extend the term of the authorization, change approval or related permit;
(i) increase or reduce the quantity of water authorized to be diverted if it appears to have been erroneously estimated.
(2) A decision maker who amends an authorization or a change approval, or a permit related to either, may substitute a new authorization, change approval or related permit, as applicable, with the same precedence as the original authorization, change approval or permit, or the original authorization, change approval or permit as modified, as applicable, subject to prescribed terms and conditions and on the terms and conditions that decision maker considers advisable.
(3) On application, the comptroller or a water manager may amend an authorization and a permit issued in relation to the authorization, and the comptroller, a water manager or an engineer may amend a change approval and a permit issued in relation to the change approval, to make an amendment not referred to in subsection (1), other than an amendment that would increase the quantity of water authorized to be diverted.
(4) The decision maker under subsection (3), with the written consent of the holder of the authorization, may substitute a new authorization or permit subject to prescribed terms and conditions and on the terms and conditions the decision maker considers advisable.
(5) Despite subsection (1) (g), a decision maker may not
(a) authorize a change in water use purpose for dedicated agricultural water except to another qualifying agricultural use, or
(b) issue a licence to a person to whom section 6 (4) [use of water — excluded groundwater users] applies.
(6) If an application is made under subsection (1) (h) to extend the term of an authorization, change approval or permit before the date the authorization, change approval or permit expires, the authorization or change approval, as applicable, and any permit issued in relation to either, does not expire until the later of
(a) the date the decision maker decides on the application, and
(b) the expiry date of the authorization, change approval or permit, as applicable.
(7) Despite subsection (1) (h), a decision maker may not amend a use approval to extend the term beyond 24 months from the date the use approval was issued.
Read the Water Sustainability Act on BC Laws ↗