Water Sustainability Act, SBC 2014, c. 15

Section 21

When final licence may be issued

Cite as Water Sustainability Act, SBC 2014, c. 15, s. 21 · read from BC Laws on November 17, 2026

The text

(1) On application under section 12 [application and decision maker initiative procedures], or on the comptroller's or water manager's own initiative, the comptroller or a water manager may issue to the holder of a conditional licence a final licence authorizing the diversion or use of the quantity of water that the decision maker determines to have been beneficially used for the water uses purposes authorized under, and during the term of, the conditional licence, when (a) the licensee completes the works, or (b) the period for completing the works expires and, if any works have not been completed, the decision maker determines that the works that have not been completed are not required. (2) On the issue of a final licence, the conditional licence it replaces has no further effect.