The abandonment, suspension, termination or cancellation of all or part of the rights held under an authorization or change approval, or all or part of the permission held under a change approval, permit or drilling authorization, does not relieve any of the following persons of liability for damage resulting from the works owned, operated or maintained by the person, or from a defect, insufficiency or failure of those works:
(a) the owner of the land, mine or undertaking to which the authorization, change approval, permit or drilling authorization is or was appurtenant;
(b) the holder or former holder, as applicable, of the authorization, change approval, permit or drilling authorization.