Direction to the British Columbia Utilities Commission Respecting the Authority's TMP Program, B.C. Reg. 139/2015

Section 3

TMP program

Cite as Direction to the British Columbia Utilities Commission Respecting the Authority's TMP Program, B.C. Reg. 139/2015, s. 3 · last amended July 15, 2015 · read from BC Laws on November 17, 2026

The text

(1) Subject to subsection (2), in setting rates for the authority, the commission must not disallow for any reason the recovery in rates of the costs incurred by the authority in carrying out the TMP program. (2) The costs recovered by rates referred to in subsection (1) must not exceed $100 million. (3) The commission must, in regard to the DSM regulatory account, allow the authority to defer to that account the authority's costs incurred as a result of carrying out the TMP program.
Read the Direction to the British Columbia Utilities Commission Respecting the Authority's TMP Program on BC Laws ↗

Made under Utilities Commission Act, RSBC 1996, c. 473.