Gas Safety Regulation, B.C. Reg. 103/2004
Section 41
Requirements for blasting in vicinity of gas installation
Cite as Gas Safety Regulation, B.C. Reg. 103/2004, s. 41 · last amended May 1, 2025 · read from BC Laws on November 17, 2026
The text
(1) A person who intends to blast in the vicinity of a gas installation must
(a) comply with sections 37 to 39, and
(b) notify the relevant gas company at least 3 business days before blasting.
(2) If a person has already complied with sections 37 to 39 and discovers in the process of construction that blasting is required, the person must notify the relevant gas company at least 24 hours, counted only on business days, before blasting is to start.
Read the Gas Safety Regulation on BC Laws ↗
Made under Safety Standards Act, SBC 2003, c. 39.