The text

In this Part: “approval” includes a certificate, licence, permit or other authorization; “prohibited projects” means (a) a project of the authority, referred to in Schedule 2 of this Act, for electricity generation on a stream, and (b) a project for electricity generation on a stream with a storage capability in excess of a prescribed storage capability, but does not include the two-rivers projects; “stream” has the same meaning as in section 1 (1) of the Water Sustainability Act; “two-rivers projects” means (a) the authority's facilities, on the Peace River and the Columbia River System, existing on the date this section comes into force and upgrades or extensions to those facilities, and (b) the project commonly known as Site C.