Energy Resource Activities Act, SBC 2008, c. 36
Section 24
Application for permit and authorization
Cite as Energy Resource Activities Act, SBC 2008, c. 36, s. 24 · read from BC Laws on November 17, 2026
The text
(1) Subject to subsection (4), a person may apply to the regulator for a permit by submitting, in the form and manner the regulator requires,
(a) a description of the proposed site of the energy resource activity,
(b) the information, plans, application form and records required by the regulator,
(c) a written report, satisfactory to the regulator, regarding the results of the consultations carried out or notification provided under section 22, if any,
(d) the prescribed information,
(e) the prescribed records, and
(f) the security required under section 30.
(2) An application for a permit under subsection (1) may be consolidated with an application for an authorization.
(3) Despite anything in a specified enactment, the regulator may not grant an authorization to a person for a related activity unless the person meets the prescribed requirements.
(4) A person may not submit an application for a permit to drill or operate a well, other than a water source well, unless
(a) the person is the owner of the petroleum and natural gas rights or is the holder of the location in respect of the well,
(b) the person has an agreement with the owner or the holder of the location referred to in paragraph (a) authorizing the drilling or operation, as applicable,
(c) the person is the holder of a storage reservoir licence issued under section 130 of the Petroleum and Natural Gas Act, or
(d) the minister has approved the submission under subsection (5).
(5) For the purposes of subsection (4) (d), the minister may
(a) approve the submission by a person of an application for a permit to drill a well if the well is to be drilled for exploratory or research purposes only, and
(b) in approving a submission under paragraph (a), declare that, if a permit is issued to the person on the basis of the submission, the person is not required to be an owner or holder referred to in subsection (4) or have the agreement referred to in that subsection in order to drill or operate the well for the purposes referred to in paragraph (a).
Read the Energy Resource Activities Act on BC Laws ↗